JUDGMENTS

Criminal Trial No. 40 of 2025

[Sentencing – Section 12(1)(g) of the Passports Act, Chapter 146 and punishable under section 12(1) of the section of the same – without lawful authority, has in his possession any passport or internal travel document issued for the use of some person other than himself – Section 109 Penal Code – Punishment of abetment if act abetted is committed in consequence and where no express provision is made for its punishment – Section 466 Penal Code – Forgery of record of Court or of public register etc – Plead guilty – Appropriate Sentence – Commencement of Sentence.]

Date of Sentence: 18 Sep 2025
Criminal Trial No. 43 of 2025

[Sentencing -Two charges – Section 451 PC read with section 34 PC – Common intention to commit House trespass with the intention to commit theft an offence punishable with imprisonment – Section 379 PC read with section 34 of the same- Theft of a car – Plead guilty – clean record – Public Interest – Deterrence sentence – Appropriate Sentence. ]

Decision date: 11 Feb 2026
Civil Appeal No. 15 of 2025

[Appeal allowed – Landowner’s claim for liquidated and ascertained damages (“LAD”) for delay in Practical Completion in a Development Project, certified by Project Architect to be 16 March 2020, summarily determined in Developer’s favour under O.14A, RSC (“determination of question of law or construction”), and, had it been necessary to do so, would have been struck out under O.18, r.18(1)(a) RSC (“no reasonable cause of action”)

Disposal: Judgments below set aside and Landowner’s claim dismissed; Costs – Landowner to pay Developer’s costs of appeal and below on standard basis, to be agreed within 28 days, failing which to be determined by the Registrar.

‘Conclusive Evidence’ clause- Cl. 2.7 of Development Agreement provided that “Any certification for extension of time in respect of the Development Project given by the Project Architect … shall be final, conclusive and binding on the parties hereto.”

If given effect, Project Architect’s certificate (“the Certificate”), dated 15 June 2022, granting an extension of time (“EOT”) to 16 March 2020, meant that there was no delay, so that the Landowner’s claim for LAD must fail.

Developer applied for EOT on 9 March 2022, almost 2 years after Practical Completion, but relatively promptly after Landowner had claimed LAD on 10
February 2022.

No general rule as to the meaning of a conclusive evidence clause, such as Cl. 2.7 – each clause turns on its own true construction – the foundation for reliance on the expertise of an expert to give a final, conclusive and binding determination is purely contractual – accordingly, a Court is dutybound, subject to well-settled exceptions, to give effect to the bargain made by the parties; it is not for the Court to make some different bargain for the parties.

Only or principal ground for Landowner resisting application of Cl. 2.7 was allegation of bad faith – but the only basis for the allegation of bad faith was the mere timing of the Developer’s application for an EOT and of the Project Architect’s certificate granting an EOT; allegation of bad faith akin to allegation of fraud and treated as such; Court held there was not any or any sufficient foundation for an allegation of fraud; accordingly, no (realistically) arguable basis for this allegation of fraud/bad faith.

No allegation of manifest error, nor could there have been; no challenge to the certificate as such.

No reasonably arguable basis for allegation (insofar as pursued) that Project Architect had materially departed from his instructions; no contractual provision
stipulating time period within which an EOT was to be sought or certified.

Accordingly, Cl. 2.7 to be given final, conclusive and binding effect; Developer entitled to summary determination in its favour.]

Decision date: 27 Aug 2026
Civil Suit/COM No. 34 of 2022

[party and party costs – assessment of costs – costs follow the event – judicial discretion costs – reasonable cost – reasonably incurred – reasonable amount – Proportionality – legal complexity – factual complexity – volume of documents – witness preparation – conduct of parties costs – repeated adjournments]

Ruling date: 8 Aug 2026
Civil Suit No. 49 of 2019

[Negligence – Workplace Accident – Personal Injury – Assessment of Damages – Quantum -Pain, Suffering and Loss of Amenities – Fractures – Permanent Deformity – Residual Disability – Limp – Scarring – Psychological Injury – Emotional Distress – Absence of Expert Evidence – No Separate Award – Special Damages – Loss of Earnings – Repatriation – Causation – Proof of Loss – Mitigation – Loss of Earning Capacity – General Damages – Labour Market Disadvantage – Permanent Handicap – Medical Expenses – Future Medical Expenses – Litigation Expenses – Costs]

Decision date: 8 Aug 2026
Civil Appeal No. 117 of 2020

[Civil Procedure — Rules of the Supreme Court — Order 21 rule 2(6) — Automatic discontinuance — Default judgment — Interlocutory judgment — Assessment of damages — Multiple defendants — Continuing proceedings — Step or proceeding in the action — Construction of Rules — Order 37 rule 3 — Whether procedural steps taken against remaining defendant constitute “any step or proceeding in the action” — Interaction between Order 21 rule 2(6) and Order 37 rule 3 — Extension of time under Order 21 rule 2(8). ]

Decision date: 4 Aug 2026
Criminal Appeal No. 26 of 2025

[Criminal Law – Sentence – s.509 Penal Code (Cap. 22) – Word, gesture, or act intended to insult the modesty of a woman – Appeal against sentence – Manifest inadequency – Sentencing principles – Technology-facilitated invasion of privacy – Covert recording in place of expected privacy – General deterrence and denunciation – Aggravating and mitigating factors – Appellate guidance – Appropriate starting point – Appeal allowed]

Decision date: 4 Aug 2026
Civil Suit No. 88 of 2021

[Claims arising out of a construction project – by the developer for liquidated damages for delay and damages for defects – by the contractor for return of retention monies and damages for delay by the developer – consideration of evidence of delay – terms of the contract – whether any defects attributable to the contractor.]

Decision date: 27 Jul 2026
Civil Suit No. 12 of 2022

[Claims arising out of a construction project – by the developer for liquidated damages for delay and damages for defects – by the contractor for return of retention monies and damages for delay by the developer – consideration of evidence of delay – terms of the contract – whether any defects attributable to the contractor]

Decision date: 27 Jul 2026
Criminal Motion No. 19 of 2025

[Criminal law – House trespass with intent to commit theft – Multiple offences – Whether individual sentences appropriate – Individual sentences within established sentencing range – Offender of previous good character – Plea of guilty at first reasonable opportunity – Whether aggregate sentence manifestly excessive – Totality principle – Application for extension of time to appeal granted – Appeal allowed.]

Judgment date: 30 June 2026
Criminal Appeal No. 6 of 2026

[- Criminal Law – Sentence appeal – Prosecution appeal against sentence – Manifest inadequency – Principles governing appellate intervention

– Criminal Law – Outraging modesty – Section 354 Penal Code (Cap. 22) – Sentencing principles

– Criminal Law – Sentencing – Departure from guideline sentence – Requirement for reasons – Aggravating factors justifying higher starting point]

Decision date: 4 Jul 2026
Criminal Trial No. 50 of 2025

[Criminal Law – Sentencing – 2 charges under s.457 of the Penal Code, Cap 22 – Housebreaking at night with intention to commit theft – 1 charge under section 379 of the Penal Code – theft of a vehicle – sentence to reflect the seriousness of the offence and to protect the public – pleas of guilty – previous convictions – deterrent sentence.]

Decision date: 1 Jul 2026
Civil Appeal No. 2 of 2026

[Probate and Administration Act s.42 – appeal from dismissal of application to appoint an administrator – necessity and expediency of such an appointment – relevance of previous findings as to conduct of the parties- undertaking given by Respondent not to dissipate assets- whether grounds for challenge to judge’s decision – Appeal dismissed with indemnity costs – stay on further action in Probate proceedings until costs paid.]

 

Judgment date: 25 June 2026
Criminal Motion No. 26 of 2025

[Criminal law – Child abuse – Significant aggravating features – Young and vulnerable victim – Serious and extensive injuries – Prolonged course of offending- Abuse of trust -Attempt to conceal offending – Personal circumstances of limited mitigating weight – Sentence neither manifestly excessive nor wrong in principle – Application for extension of time to appeal dismissed – Substantial delay in disposal of case – Timely disposal of criminal proceedings a matter of public importance.]

Judgment date: 24 June 2026
Originating Summons No. 71 of 2025

[Arbitration – Foreign arbitral award – Recognition and enforcement – Whether prior registration required before reliance on award in insolvency proceedings – Insolvency – Winding-up – Statutory demand – Whether unregistered foreign arbitral award can constitute evidence of debt – Distinction between enforcement and proof of debt]

Decision date: 22 Jun 2026

About GOV.BN  |  Research Us   |  Rate this Website

Digital Services

Overview of Digital Government

Digital Government Strategy & Initiatives

Digital Government Strategic Plans & Legislation

Other Information

Circular & Policy

Tenders & Quotations

TPOR for Government Agencies

Privacy Statement  |  Terms of Use  |  Disclaimer

Copyright Goverment of Brunei Darussalam. All Right Reserved.